(Created page with "{{this}} measures the time that equipment or a factory is operating (being utilized) as a percentage of its maximum potential capacity. ===Calculation=== {{math|{{this}}|{{fr...")
 
 
Line 1: Line 1:
{{this}} measures the time that equipment or a factory is operating (being utilized) as a percentage of its maximum potential capacity.  
+
{{this}} measures the time that production assets, equipment or a factory is operating (being utilized) as a percentage of its maximum potential capacity.  
 
===Calculation===
 
===Calculation===
 
{{math|{{this}}|{{frac|Planned Production Time|Total Time|100 %}}}}
 
{{math|{{this}}|{{frac|Planned Production Time|Total Time|100 %}}}}
{{where|%|[[m:AE311]]|The percentage of time the equipment is ready and able to run, excluding planned and unplanned downtime.|[[m:AE312]]|The percentage of time the equipment is running at its maximum speed, without minor stops or slow cycles.|[[m:AE313]]|The percentage of good parts produced, excluding defects or rework.
+
{{where|%|Planned Production Time|The time production assets/equipment is planned to operate in days or hours.|Total Time|365 days or 365 x 24 hrs.}}
}}
 
 
===Importance===
 
===Importance===
{{this} provides insights in how much potential you have to increase throughput with the equipment you already own.
+
{{this}} provides insights in how much potential you have to increase throughput with the equipment you already own.
 
===Notes===
 
===Notes===
 
{{this}} has an inverse relationship with average cost of goods or cost per unit – the higher the utilization rate, the lower the average cost of goods and vice versa.
 
{{this}} has an inverse relationship with average cost of goods or cost per unit – the higher the utilization rate, the lower the average cost of goods and vice versa.

Latest revision as of 18:10, 26 February 2025

Capacity Utilization measures the time that production assets, equipment or a factory is operating (being utilized) as a percentage of its maximum potential capacity.

Calculation

Capacity Utilization
=
Planned Production Time   × 100 %
Total Time
where:
  • Planned Production Time = The time production assets/equipment is planned to operate in days or hours.
  • Total Time = 365 days or 365 x 24 hrs.
Unit of Measure: %

Importance

Capacity Utilization provides insights in how much potential you have to increase throughput with the equipment you already own.

Notes

Capacity Utilization has an inverse relationship with average cost of goods or cost per unit – the higher the utilization rate, the lower the average cost of goods and vice versa.

Community Importance Rating:
0.00
(0 votes)

Hierarchy

IDNameLevelx
AE3Total Equipment Efficiency Performance1AE3
AE32Capacity Utilization2AE32
Capacity Utilization Total Equipment Efficiency Performance 53200 2 Capacity,Utilization,Productivity,Equipment,Performance,Manufacturing,Make,OEE The ratio between the total available time and the loading time.